浅议给排水关于建筑工程给排水系统安装与施工技术
最后更新时间:2024-02-15
作者:用户投稿本站原创
点赞:6103
浏览:16318
论文导读:
摘要:伴随科技飞速的发展,建筑工程的给排水系统的生产工艺也在不断的提高和改进,并且排水工程朝着高参数、大系统方向发展,所以,在对给排水工程进行设计、维修、运行管理和施工时的要求也就越发的高。要想确保系统的高效、优质和低能耗,除了系统设计必须良好之外,还要确保给排水系统的安装质量。文中就建筑工程中给排水系统的安装和施工技术作了大致的论述,以期对我国的建筑工程事业在给排水系统方面提供可供参考的意见和建议。
关键词:建筑工程;给排水系统;安装;施工设计
Abstract: with the rapid development of science and technology, the construction of the water supply and drainage system in the production process of continuous improvement and improve, and drainage works toward a high parameters, system development direction, so, in the water supply and drainage engineering design, maintenance, operation management and construction requirements of the high. If you want to ensure that the system of high efficiency, high quality and low energy consumption, in addition to system design must be good, but also to ensure water supply and drainage system installation quality. The construction of water supply and drainage system installation and construction technology, this paper discusses the general, in order to China's construction industry in water supply and drainage system to provide reference opinions and Suggestions.
Keywords: building engineering; Water supply and drainage system; Installation; Construction design.
2095-2104(2013)
要求:
(二)在管道的安装施工过程以及完工之后,要将施工技术的资料表格进行及时的填写并要进行签证记录,对于埋地铺设管道,要对其进行隐蔽工程验收,将隐蔽工程记录予以填写并及时进行回填,假如管道内有给水立管要对其实行试压试验,在验收合格之后才能隐蔽,并且这些技术资料要整理存档。
(三)对穿过基础、墙壁和楼板的管道,要用套管对其进行保护,并且在套管之内不能有管道的接口,套管和管道间的间隙要使用阻燃材料进行填塞。
(四)当管道安装中断之时,要用麻袋将管道敞开端口裹好,当管道井内立管安装中断之时,要用厚木板搭在管道井上方,从而避免大杂物进入。
(五)在连接PP-R管热溶时,把管件和管道水平插进热溶机中,在加热完成之后管件和管道要立刻脱离热溶机,并使用外力把管道推进管件里。在安装PP-R管道之时,要采取一定的措施对其伸缩性加以预防。
(二)要对水平干管和排水主干管管道做通球通水试验,并确保通球的球径不能比排水管的管道直径三分之二小,与此同时,通球率必须为百分之百。
(三)支管送至用水点的标高和位置要与设计要求相符,生活污水管道坡度要与规范要求或设计要求相符。
(四)排水立管上面每隔一层需设置一检查口,但在最高层和最低层一定要设置检查口,它的中心高度离地面的距离为一米,并允许有二十毫米的偏差,检查口朝向要方便检修,要将检查门安装在暗敷立管检查口处。
(五)在施工完成之后,要对隐蔽管道做灌水实验,在隐蔽之前要请监理单位和质监部门进行验收。
摘要:伴随科技飞速的发展,建筑工程的给排水系统的生产工艺也在不断的提高和改进,并且排水工程朝着高参数、大系统方向发展,所以,在对给排水工程进行设计、维修、运行管理和施工时的要求也就越发的高。要想确保系统的高效、优质和低能耗,除了系统设计必须良好之外,还要确保给排水系统的安装质量。文中就建筑工程中给排水系统的安装和施工技术作了大致的论述,以期对我国的建筑工程事业在给排水系统方面提供可供参考的意见和建议。
关键词:建筑工程;给排水系统;安装;施工设计
Abstract: with the rapid development of science and technology, the construction of the water supply and drainage system in the production process of continuous improvement and improve, and drainage works toward a high parameters, system development direction, so, in the water supply and drainage engineering design, maintenance, operation management and construction requirements of the high. If you want to ensure that the system of high efficiency, high quality and low energy consumption, in addition to system design must be good, but also to ensure water supply and drainage system installation quality. The construction of water supply and drainage system installation and construction technology, this paper discusses the general, in order to China's construction industry in water supply and drainage system to provide reference opinions and Suggestions.
Keywords: building engineering; Water supply and drainage system; Installation; Construction design.
2095-2104(2013)
一、给排水系统管道安装的施工步骤
对图纸和相关技术资料加以熟悉;施工测量放线;开挖沟槽以及砌筑管沟;与土建相配合进行预埋铁件和预留孔洞;对管件进行加工制作;制作和安装支架;预制和组成管道;管道的敷设安装;将管道和设备进行连接;安装自控仪表;清洗和试压;保温和防腐;试运转和调试;竣工验收。二、给排水系统的给水设备安装
以下各部分共同构成了室内的给排水系统:阀门器件、分支管、立管、水平主干管、供水设备、水表节点、引入管。由于水泵房内的阀门和水泵等是用水的枢纽,安装质量良好才能确保工程供水系统供水系统能运作良好,因此对安装提出如下的源于:论文结论www.7ctime.com要求:
(一)在安装设备之前要对相关文件合格证和资料进行检查核对。
(二)确保设备无锈蚀、损坏和缺件,并且转动部分必须灵活,无卡住、阻滞现象和异常声音。
(三)安装设备机组之时要根据已确定的机组长度尺寸、机组台数和水泵机组型号来对其在水泵房里的纵横排列形式和安装位置进行合理的规划。在对机组进行布置之时要使弯头最少,管线最短,并且管路要方便连接以及留有一定空间和走道,从而便于维修、操作和管理。三、给排水系统给水管道安装
(一)在安装管道之前需要对管道地沟进行复测,看支架是否与管道安装坡向、坡度和标高相论文导读:米。(二)要对水平干管和排水主干管管道做通球通水试验,并确保通球的球径不能比排水管的管道直径三分之二小,与此同时,通球率必须为百分之百。(三)支管送至用水点的标高和位置要与设计要求相符,生活污水管道坡度要与规范要求或设计要求相符。(四)排水立管上面每隔一层需设置一检查口,但在最高层和最低层一定要设置
符。要确保安装好后的管道竖直、横平,立管垂直度及纵横方向弯曲等偏差要与管道运行和放空的工艺需要相符。(二)在管道的安装施工过程以及完工之后,要将施工技术的资料表格进行及时的填写并要进行签证记录,对于埋地铺设管道,要对其进行隐蔽工程验收,将隐蔽工程记录予以填写并及时进行回填,假如管道内有给水立管要对其实行试压试验,在验收合格之后才能隐蔽,并且这些技术资料要整理存档。
(三)对穿过基础、墙壁和楼板的管道,要用套管对其进行保护,并且在套管之内不能有管道的接口,套管和管道间的间隙要使用阻燃材料进行填塞。
(四)当管道安装中断之时,要用麻袋将管道敞开端口裹好,当管道井内立管安装中断之时,要用厚木板搭在管道井上方,从而避免大杂物进入。
(五)在连接PP-R管热溶时,把管件和管道水平插进热溶机中,在加热完成之后管件和管道要立刻脱离热溶机,并使用外力把管道推进管件里。在安装PP-R管道之时,要采取一定的措施对其伸缩性加以预防。
四、给排水系统的排水管道安装
(一)因为U-PVC排水管的膨胀吸水比较大,所以管道污水温度和环境温度变化造成的伸缩很大,在对排水管进行固定之时一定要按照设计要求来装设伸缩节,假如设计没有要求之时,伸缩节之间的距离不能大于四米。(二)要对水平干管和排水主干管管道做通球通水试验,并确保通球的球径不能比排水管的管道直径三分之二小,与此同时,通球率必须为百分之百。
(三)支管送至用水点的标高和位置要与设计要求相符,生活污水管道坡度要与规范要求或设计要求相符。
(四)排水立管上面每隔一层需设置一检查口,但在最高层和最低层一定要设置检查口,它的中心高度离地面的距离为一米,并允许有二十毫米的偏差,检查口朝向要方便检修,要将检查门安装在暗敷立管检查口处。
(五)在施工完成之后,要对隐蔽管道做灌水实验,在隐蔽之前要请监理单位和质监部门进行验收。